A case of advantage on maturing the Kanban board



Organizations new to Kanban that have no experience with Agile usually find it easier to design 
their boards than those with Agile background because Kanban recommends the board to reflect 
the actual process rather than an abstraction. Compare for example Board 1a, quite common in 
agile practices, with Board 1b. 

Board 1a  

Board 1b 

This is a good start. As we all know, a project’s behavior changes over time. This means the 
Kanban board should keep up with those changes, but unfortunately many Kanban 
organizations don’t go about keeping the board up to date and that has undesirable 
consequences such as fake visualization and forcing the real process to adjust to he board 
process. Both of them affect quality and value delivery. Oh but there’s more to it. We miss big 
time on the identification of opportunities for improvement.
 I will illustrate the benefits of keeping the board up to date through a real case. One of my 
customers is a small Telecom business that provides technical services to some of the biggest 
Telecoms in the world. The very first coaching session I gave them right after finishing Kanban 
training consisted on helping them create their first functional Kanban board. As a coach I didn’t 
build the board for them, of course, but rather had them create it providing guidance as I saw it 
necessary. During that session I realized that the last portion of their process was convoluted so 
I decided to dig into process details with them rather than focusing on creating the board. 
Throughout the discussion the team agreed that part of the process was suboptimal and I made 
a recommendation which we agreed upon and so the first Kanban board was created reflecting 
the actual process but already suggesting a small but important change at the end. The change 
had to do with the customer verification phase.
I visited them to do a second round of coaching and was very pleased to see they had modified 
the board to be a show on Board 2a. I asked to a team member to explain the board to me and 
he did a pretty good job; and at the same time I noticed some hesitation explaining the sub-
column labeled “Pending”. I decided the to dig in to it. Discussing this with the team it became 
clear that it had to do with dependencies they had with their subcontracted providers as well as 
with internal dependencies, and their cycle time was being affected by it. 

Board 2a  

I then suggested to them to further visualize “Pending”. The result was Board 2b. We added a new
column to visualize de 3 subcontracted providers and also kept de original sub-column which was
to be used only for internal dependencies. 

Board 2b  

This change allowed to better understand the behavior of each subcontractor a well as to see how
the customer was taking care of its own dependencies. The subcontractors behavior was quantified
(the rest of the process had been quantified before from the beginning) and that allowed to show
them how their response time affected final delivery. This motivated the subcontractors to improve,
one of them started adopting Kanban also, and that resulted in significant improvement on delivery
to customer. This also motivated a behavioral change on the team itself to take care of their internal
dependencies more efficiently. The rend result was an increase of on-time delivery to customer from
86% to 99%.

Additional benefits surfaced from this such as the obtention of more contracts without having to 
increase staff.

--Masa K Maeda